A step-by-step guide to planning, controlling, monitoring and analysing budgets in Klirr: from creating a budget and getting it approved, through changes after approval and actuals, to forecasts, risks, findings and reports. Every step shows the real screen, who may do it, the exact permissions and what changes afterwards.

Versjon
2.0.1
Oppdatert
Kapitler
13
leksjoner
63

Kapittel E

Actuals and commitments

Where the actual and committed amounts come from, which statuses count, and when figures refresh.

How actual amounts enter Budget Intelligence #

  • Source: general-ledger journal lines with status Posted or Reversed. A reversal and its original net to zero.
  • Sign: following the account's normal balance — cost accounts grow with debits, revenue accounts with credits, so both show positive actuals.
  • Matching: account and cost centre, profit centre and project must be exactly the same as the budget line (an empty dimension matches only postings without that dimension).
  • Date: posting date inside the line's window (its month, or the fiscal year for whole-year lines). Budget Intelligence cuts the window at today; the Budget vs actual reports use the whole fiscal year.
  • Currency: the journal line's base-currency amount (company accounting currency).
  • Payroll, expenses and supplier invoices reach Actual only through their posted journals. Draft or unposted documents are never actual.
  • Activity on budgeted accounts with a combination no line has is shown separately as "Unbudgeted activity" and blocks certification above the tolerance.

Drill-down from Actual: every row is a posted journal line; "Reconciles" confirms the total equals the figure on screen.

How commitments are calculated #

Source documentCounts as open commitment when…Stops counting when…
Supplier bill (without order)Status Draft, PendingMatch, MatchException, PendingApproval, ChangesRequested, Approved or ReadyToPostPosted, PartiallyPaid or Paid (now actual); Rejected, Cancelled or Credited (excluded)
Purchase requestApproved (commitment opened)Cancelled or rejected; replaced by the purchase order
Purchase orderApproved / sent; remaining = base − invoiced (net of credits)Invoiced (consumed by posted bills), cancelled, or closed when fully invoiced
Budget control holdA document passed the control checkThe document's commitment or posting confirms it, it is released, or verified expired
Manual reservationPending, Reserved or PartiallyConsumed (amount − consumed)Consumed, released or cancelled
  • No double counting: a supplier-bill line on an order line that already has a commitment is left out of the bill commitment.
  • Quantity credit notes reopen the order commitment; price credits do not.
  • Bills in another currency are converted with their exchange rate; a bill without a rate is left out and the line is marked "commitment incomplete".
  • Demo: SB-00000055 "Office cleaning, monthly", PendingApproval, 2,400.00 → open commitment on 40 Cost of goods sold, October.

When figures refresh #

Live at page load

Approved, Released, Actual, Open commitment, Available, Headroom (Availability tab, drill-downs, dashboard tiles).

Last calculation

Forecast at completion, forecast variance, utilisation, risks, findings, certification, data coverage.

Nightly

Automatic calculation for every budget at 00:00 UTC (missed runs caught up within 24 h). New postings and commitments do not trigger a calculation by themselves.

Immediately

People's changes recalculate at once: approval, movements, revisions, carry-forward, reservations — and Recalculate / Run Budget Intelligence.

Nightly 03:00 UTC

Queued automatic analyses (Investigate) that were not run on request.

Tip: read "Last calculated" (Availability tab) and the dashboard warning box before relying on forecasts or risks.